Completed: May 2002
Challenges: Completing the job according to a rigorous schedule,
including working through elements of winter weather
Services Provided: Fabrication and installation of all steel
stairs, rails and miscellaneous steel items for the project
Completed: June 2001
Challenges: Design/Build a project with constant changes;
flexibility to accommodate design changes; completing the
project within time and budget constraints
Services Provided: Advance Welding & Fabricating constructed
two 18-story stair towers and provided miscellaneous steel
items for the project
Completed: 1986
Challenges: Large project, new type of construction for the
area; logistics of installing up to 2 miles of rails and railings;
bringing the project in on-time and under budget
Services Provided: Fabricated and installed all stairs and
railings for entire project, interior and exterior
Phase 1: Completed September 2000
Phase 2: Completed October 2002
Challenges: Complete demolition of existing
#3 and #4 antiquated boilers; structural steel modifications
and reinforcing, to support new boiler load
Services Provided: Structurally reinforced the existing loading
dock for the increased load; developed and installed a track
system to place new boiler; coordinated two cranes to pick
up and set new boiler off rail cart; designed, fabricated
and installed new boiler stack.
|